Are there time periods for lien claims?

Yes, the Construction Lien Act has many strict deadlines. Claimants have 45 days to “preserve” their lien claims and then another 45 days to “perfect” their claims. Claimants must set their lien claims down for a trial within two years of issuing the Statement of Claim.